Chief Executive Engineer, Lower Pus Project (Minor Irrigation Division), Yavatmal And Another v. Devkabai Daulatrao Dhoke And Others
1 CAF2145.18
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH : NAGPUR CIVIL APPLICATION (CAF) NO. 2145 OF 2018 IN FIRST APPEAL (ST.) NO. 16612 OF 2017 The Chief Executive Engineer, Yavatmal and anr. ..VS..
Devkabai Daulatrao Dhoke and others.
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Office Notes, Office Memoranda of Coram, Court's or Judge's orders appearances, Court's orders of directions and Registrar's orders - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Shri R.C. Raibhandare, Advocate for appellant/applicant. Shri A.B. Nakshane, Advocate for respondent No. 1 Shri H.D. Dubey, AGP for respondent Nos. 2 & 3. CORAM : M.G.GIRATKAR,J.
DATED : 17th JUNE, 2019.
Heard.
The delay is of 264 days which is caused due to administrative difficulties and the entire amount of award is deposited before reference Court.
Looking to the administrative difficulties mentioned in the application, the application is allowed. The delay is condoned. Appeal be registered.
FIRST APPEAL (ST) NO. 16612 OF 2017 Admit.
Advocate Shri Nakshane waives notice for respondent No. 1 and learned AGP Shri Dubey waives notice for respondent Nos. 2 & 3.
Put-up this matter after one week.
Prity G.
JUDGE