Vidarbha Irrigation Development Corporation, Through Its Executive Engineer, Khadakpurna Project v. Anantabhanudas Shigne And 2 Others
1 cao1521.17
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH : NAGPUR C.A.O. NO.1521/2017 AND M.C.A. STAMP NO.16970/2017 IN FIRST APPEAL NO.750/2014 Vidarbha Irrigation Development Corporation, through Executive Engineer, Khadakpurna Project, Tah. Deulgaonraja, Distt. Buldhana ..Vs..
Ananta Bhanudas Shingne and others - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Office Notes, Office Memoranda of Coram, Court's or Judge's orders appearances, Court's orders of directions and Registrar's orders - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Ms. J.J. Alkari, Advocate h/f Shri N.M. Gaidhane, Advocate for the applicant / appellant.
CORAM : Z.A. HAQ, J.
DATE : 22.3.2018.
Heard.
Accepting the explanation given in the application, delay of 714 days in filing the restoration application is condoned, the first appeal is restored. The civil application and miscellaneous civil application are allowed accordingly. No costs.
FIRST APPEAL NO.750/2014 Shri K.S. Narwade, Advocate waives notice for respondent No.1.
Ms. Mayuri Deshmukh, A.G.P. wavies notice for respondent Nos.2 ad 3.
The appellant to file private paper book within six months.
The learned Advocates for the respective
2 cao1521.17 parties state that the matter be placed before the National Lok-Adalat, Nagpur scheduled on 14th April, 2018.
The parties to appear before the National Lok-Adalat, Nagpur on 14th April, 2018 at 11 a.m. JUDGE Tambaskar.