The Executive Engineer, Lower Wardha Project Division, Wardha v. Arun S/O Bhaurao Falke And Others
fa200.16.O.odt 1
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR FIRST APPEAL NO.200 OF 2016 (Executive Engineer, Lower Wardha Project Division, Wardha Vs. Arun Bhaurao Falke and others) --------------------------------------------------------------------------------------------------------------------------------- Office Notes, Office Memoramda of Coram, appearances, Court's orders of directions Court's or Judge's orders.
and Registrar's Orders.
--------------------------------------------------------------------------------------------------------------------------------- Shri Anoop Parihar, Advocate for Appellant.
Shri S.D. Chopde, Advocate for Respondent Nos.1 to 3. Ms. Shamsi Haider, AGP for Respondent Nos.4 & 5. CORAM: DR. (SMT.) SHALINI PHANSALKAR-JOSHI, J. DATE: 4 th AUGUST, 2017.
Civil Application (F) No.3295/2017:
This is an application filed by the claimant for withdrawal of the entire amount of compensation which is to the tune of Rs.41,45,277/-. Considering the enhancement awarded by the Reference Court, it is requested by learned counsel for appellant that the amount be permitted to be withdrawn subject to furnishing of usual undertaking and solvent surety/security.
Accordingly, respondent is permitted to withdraw the entire amount of compensation subject to furnishing of usual undertaking and also subject to furnishing of solvent surety/security for 50% of the amount. The application is disposed of.
JUDGE NSN