Executive Engineer, (V.I.D.C.), Bembla Project Division, Yavatmal v. Dinesh Sureshchandra Jaiswal And 2 Others
caf 2076.22.
1/2
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR CAF No.2076/2022 in First Appeal No.495/2015 (D) The Executive Engineer, Bembla Project, VIDC, Yavatmal V Dinesh and others ************************************************************************************* Office notes, Office Memoranda of Coram, appearances, Court's orders Court's or Judge's Orders or directions and Registrar's orders.
************************************************************************************* Ms. M. Babhulkar, Advocate for appellant.
Mr. A.B. Nakshane, Advocate for resp. no.1.
Ms. T.H. Udeshi, AGP for resps. no.2 and 3.
CORAM : ABHAY AHUJA, J.
DATE : 13-10-2022 Mr. Nakshane, learned Counsel seeks leave to withdraw Civil Application (F) No.2076/2022 in view of fresh application for withdrawal bearing Civil Application (F) No.2282/2022 filed on behalf of his client.
Leave granted.
Application stands disposed as withdrawn.
Civil Application (F) No.2282/2022 Heard.
Learned Counsel for the claimant would submit that the calculation that has been submitted by the Acquiring Body vide Pursis Stamp No.4423/2019 dated 25-03-2019 does not reflect the correct area that was acquired and as such the same may have to be appropriately modified.
Let a modified calculation sheet be submitted by the
caf 2076.22.
2/2 next date so that appropriate orders can be passed in the application.
List the matter on 10-11-2022.
(Abhay Ahuja, J.) Deshmukh