Vidarbha Irrigation Development Corporation, Through Executive Engineer, Bembla Project Division v. Shri Govind Namdev Mone And 2 Others
2024:BHC-NAG:10134 1 5caf2426.24.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH AT NAGPUR CIVIL APPLICATION [F] NO.2426 OF 2024 IN FIRST APPEAL NO.711 OF 2015 [D] [Vidarbha Irrigation Development Corporation .vs. Govind s/o Namdev Mone and others] - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Office Notes, Office Memoranda of Coram, Court's or Judge's orders appearances, Court's orders of directions and Registrar's orders - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Shri V.B. Rathi, Adv. h/f Shri P.B. Patil, Advocate for Appellant-VIDC, Shri S.V. Ingole, Advocate for Applicant-Respondent No.1, Ms. Deepa Charlewar, AGP for Respondent Nos.2 and 3. ..........
C ORAM : SANJAY A. DESHMUKH, J.
D ATE : SEPTEMBER 06, 2024.
1.
This is an application filed by the applicantrespondent no.1 for speaking to minutes. 2.
Learned Advocate for the applicant pointed out that in para no.3 of the order dated 13.08.2022, there is last sentence i.e. "The Appellant shall be entitled to withdraw the amount of compensation alongwith accrued interest, if any, after deducting the amount, if any already withdrawn, as per order of the Court. He submitted that instead of the word 'Appellant' the words 'Respondent No.1' be corrected. 3.
Considering his submissions and for the reasons mentioned in the application, the application deserves to be allowed. In para no.3 of the order dated 13.08.2022, instead of the word 'Appellant', the words 'Respondent No.1' be corrected and corrected copy be uploaded.
4.
The application is allowed and disposed of.
(SANJAY A. DESHMUKH, J.) Gulande