Executive Engineer, Lower Wardha Project Division, Wardha v. Jagdish Harishchandra Fale And 2 Others
HIGH COURT LEGAL SERVICES SUB-COMMITTEE, NAGPUR BENCH, NAGPUR. BEFORE THE NATIONAL LOK ADALAT FIRST APPEAL NO.568 OF 2017 VIDC thr. its Executive Engineer, Lower Wardha Project, Wardha
Versus
Jagdish Harishchandra Fale and others.
Shri V.G. Palshikar, Advocate for the Appellant. Ms Shamsi Haider, A.G.P. for Respondent Nos. 2 and 3.
ORDER
(Passed on 13th July 2019) Shri R.P. Varhade, Executive Engineer, Lower Wardha Project Division, Wardha is present.
The appellant has tendered pursis today, which is marked as "X" for identification.
The instant appeal is covered under the Government Regulation dated 3rdNovember, 2016, Corrigendum dated 23rd February, 2017, and Government Resolution dated 13th August, 2018, and therefore, the appellant seeks permission to withdraw the appeal.
The appeal stands disposed of as withdrawn in terms of pursis Exh. 'X'. No Costs.
The appellant shall deposit the amount of compensation before the reference Court within a period of three months from the date of award. The respondent/claimant shall be entitled to withdraw the amount of compensation, if deposited in the reference Court/High Court, along with accrued interest.
Court fees, if any, be refunded to the appellant as per rule. MEMBER MEMBER PRESIDING OFFICER (A.R. Patil) (G.M. Kubde) (Justice Vinay Joshi) Advocate Retd. P.D.J.
rkn