Bombay High CourtCAF/295/2023delay condonatedrejected

The Executive Engineer, Bembla Project Division, Yavatmal And Another v. Ramchandra Punaji Vairagade And Others

2023-03-10Hon'Ble Justice Urmila Joshi Phalke1 pages

19 caf295.23

IN THE HIGH COURT OF JUDICATURE AT BOMBAY,

NAGPUR BENCH, NAGPUR CAF NO.295/2023 AND FA ST.NO.16695/2022 The Executive Engineer, Bembla Project Division Yavatmal and anr ..vs..

Ramchandra Punaji Vairagade and ors ........................................................................................................................................................................... OfÏce Notes, OfÏce Memoranda of Coram, appearances, Court orders or directions Court's or Judge's Order and Registrar's orders ........................................................................................................................................................................... Shri T.M.Zaheer, counsel for applicants.

Shri S.C.Bhalerao, counsel for non-applicant No.1. Shri M.A.Kadu, AGP for non-applicant Nos.2 and 3. CORAM : URMILA JOSHI-PHALKE, J.

DATED : 10/03/2023 1.

By this application, the acquiring body seeks condonation of delay caused in filing the appeal. Delay is of 37 days. 2.

As per contentions of applicants, they have to obtain necessary permission and also have to obtain legal opinion before filing of appeals and, therefore, time was consumed and the delay is caused.

3.

For reasons stated in the application, the application is allowed. The delay stands condoned.

4.

Office to register the first appeal.

5.

The first appeal is admitted.

6.

Record and proceedings be called for.

7.

Paper-book be filed within eight weeks.

8.

Learned counsel for respective respondents waive service.

9.

List the appeal for its final hearing after filing of paperbook. 10.

The application is disposed of.

(URMILA JOSHI-PHALKE, J.) !! BrWankhede !!

by BHUSHAN RANA WANKHEDE Date: 2023.03.13 11:16:02 +0530 ...../- BHUSHAN RANA WANKHEDE