IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH AT NAGPUR CIVIL APPLICATION (CAF) NO. 543 OF 2018 IN FIRST APPEAL STAMP NO. 19193 OF 2017 The Executive Engineer, Purna Medium Project, Achalpur Division, Achalpur Camp, Amravati V/s Ramrao Gopalrao Nahad and others.

--------------------------------------------------------------------------------------------------------------------------------------- Office Notes, Office Memoramda of Coram, appearances, Court's orders of directions Court's or Judge's orders.

and Registrar's Orders.

--------------------------------------------------------------------------------------------------------------------------------------- Shri M.A. Kadu, counsel h/f Shri P.B. Patil, counsel for the appellant. Shri S.J. Kadu, AGP for the respondent Nos. 2 and 3. CORAM: ARUN D. UPADHYE, J.

DATE: 26-03-2019.

None appears for the respondent No.1, though served. Heard learned counsel for the appellant as well as learned AGP for the respondent Nos. 2 and 3.

Perused the application. There is delay of 489 days in filing the appeal. For the reasons stated in the application, delay is condoned. Civil application is allowed. FIRST APPEAL STAMP NO. 19193 OF 2017.

Heard.

Admit.

Call for record and proceedings.

Shri S. J. Kadu, learned AGP waives notice for the respondent Nos. 2 and 3.

JUDGE rkn