The Executive Engineer, Upper Painganga Project Division, Umarkhed, Yavatmal v. Sk. Hidayat Sk. Fakira And Others
2024:BHC-NAG:10523 16..odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH : NAGPUR CIVIL APPLICATION (CAO) NO.1151 OF 2024 IN CIVIL APPLICATION (CAF) NO.2211 OF 2024 IN FIRST APPEAL NO.150 OF 2024 The Executive Engineer, Upper Painganga Project Division, Yavatmal and others.Vs. Sk. Hidayat Sk. Fakira and others Office Notes, Office Memoranda of Court's or Judge's Order Coram, appearances, Court's Orders or directions and Registrar's order Shri M.R. Joharapurkar, Advocate for appellant. Shri A.R. Patil, Advocate for respondent No.1. Ms H.S. Dhande, A.G.P. for respondent Nos.2 and 3/State. CORAM : SANJAY A. DESHMUKH, J.
DATED : 19/09/2024 1.
This is an application for modification of order dated 19.08.2024 passed by this Court.
2.
Heard learned advocates for both sides.
3.
Perused the application.
4.
Considering reasons stated in the application, the order dated 19.08.2024 deserves to be corrected as under:
5.
Respondents/claimant No.1 is entitled to withdraw 50% amount on usual undertaking and 25% amount on solvent surety.
6.
Registry is directed to pay amount as per the above directions.
7.
The application is allowed as prayed for.
C.L. Dhakate
16..odt FIRST APPEAL NO.150 OF 2024 8.
Stand over after four weeks.
(SANJAY A. DESHMUKH, J.) C.L. Dhakate