V.I.D.C., Through Its Executive Engineer, Medium Irrigation Project Division, Yavatmal v. Gajanan Kaniram Chavhan And Others
(1) 35.caf.833.2023
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH : NAGPUR CIVIL APPLICATION (CAF) NO.833 OF 2023 IN FIRST APPEAL STAMP NO.19911 OF 2018 Vidarbha Irrigation Development Corporation, through its Executive Engineer, Medium Irrigation Project Division, Yavatmal Vs.
Gajanan Kaniram Chavhan and others ----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- Office Notes, Office Memoranda of Coram, Court's or Judge's orders appearances, Court's orders of directions and Registrar's orders ----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- Mr. S. K. Bhoyar, Advocate for applicant.
Mr. M. A. Kadu, AGP for non-applicant nos.2 and 3. CORAM :
URMILA JOSHI-PHALKE, J.
DATED : 23/03/2023 1.
By this application, the applicant is seeking condonation of delay.
2.
Issue notice to the non-applicants, returnable after four weeks.
3.
Learned AGP Mr. Kadu, waives notice for non-applicant Nos. 2 and 3.
CIVIL APPLICATION (CAF) NO.834 OF 2023 1.
Present application is filed under Order 41 Rule 5 of the Code of Civil Procedure, stay to the effect, operation and implementation of the impugned Judgment and Award passed by the Joint Civil Judge Senior Division, Yavatmal in Land Acquisition Case No.67/2008.
(2) 35.caf.833.2023 2.
On depositing the entire amount of compensation within two weeks, the effect, operation and implementation of the impugned Judgment and Award passed by the Joint Civil Judge Senior Division, Yavatmal in Land Acquisition Case No.67/2008, be stayed till final disposal of the appeal.
3.
Civil application is disposed of.
(URMILA JOSHI-PHALKE, J.) Sarkate SARKATE 13:33