← Library
Bombay High CourtCAF/3324/2023allowed

V. I. D. C. Through Its Executive Engineer, Lower Wardha Project Division, Wardha And Another v. Nilesh Shrikrushna Zade And Others

2023-11-02Hon'Ble Mrs. Justice Vrushali V. Joshi2 pages

1 / 2 20.caf3324.2023

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH : NAGPUR CIVIL APPLICATION (CAF) NO. 3324 OF 2023 IN FIRST APPEAL NO. 415 OF 2022 VIDC, Wardha and anr.

Vs.

Nilesh Shrikrushna Zade and Ors.

---------------------------------------------------------------------------------------------- Office notes, Office Memoranda of Coram, appearances, Court's orders Court's or Judge's Orders.

or directions and Registrar's orders.

---------------------------------------------------------------------------------------------- Mr. Vinay Dahat, Advocate for appellant.

Ms. M.R. Kavimandan, AGP for respondent Nos.3 & 4. CORAM : VRUSHALI V. JOSHI, J.

DATE : NOVEMBER 02, 2023.

Learned counsel for the appellant submits that 50% of the compensation amount has already been withdrawn by the respondent Nos.1 and 2.

2.

The respondent Nos.1 and 2 have filed this application to withdraw 50% balance compensation amount with accrued interest.

3.

Considering the reasons given in the application, the same is allowed.

The applicant/respondent Nos.1 and 2 are permitted to withdraw 25% of total balance compensation amount with one solvent surety.

Prity

2 / 2 20.caf3324.2023 4.

Registry is directed to release the balance amount after verifying the documents and on filing of usual undertaking.

5.

Application stands disposed of.

(MRS. VRUSHALI V. JOSHI, J.) Prity