V.I.D.C. Thr. Its Executive Engineer, Lower Wardha Project Dn v. Dilip S/O Nathamal Rathi And Oths
HIGH COURT LEGAL SERVICES SUB-COMMITTEE, NAGPUR BENCH, NAGPUR. BEFORE THE NATIONAL LOK ADALAT FIRST APPEAL NO.74 OF 2010 VIDC thr. its Executive Engineer, Lower Wardha Project Division, Wardha
Versus
Dilip Nathamal Rathi and others.
Shri U.A. Gosavi, Advocate for the Appellant. Shri I.J. Damle, A.G.P. for Respondent Nos.2 & 3.
ORDER
(Passed on 17thMarch, 2019) Shri Ravindra Varhade, Executive Engineer, Lower Wardha Project Division, Wardha is present.
The appellant has tendered pursis today, which is marked as "X" for identification.
The instant appeal is covered under the Government Regulations dated 3rdNovember, 2016 and 23rd February, 2017 and therefore, the appellant seeks permission to withdraw the appeal.
The appeal stands disposed of as withdrawn in terms of pursis Exh. 'X'. No Costs.
The appellant shall deposit the amount of compensation before the reference Court within a period of three months from the date of award. The respondent/claimant shall be entitled to withdraw the amount of compensation, if deposited in the reference Court/High Court, alongwith accrued interest.