V.I.D.C, Through Its Executive Engineer, Amravati Project Construction Division, Amravati v. Narayan S/O Tukaram Ghormode And Others
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR.
CIVIL APPLICATION (CAF) NO.2552 OF 2022 IN FIRST APPEAL ST NO.18676 OF 2022 V.I.D.C, THROUGH ITS EXECUTIVE ENGINEER, AMRAVATI PROJECT CONSTRUCTION DIVISION, AMRAVATI VS NARAYAN S/O TUKARAM GHORMODE AND OTHERS ______________________________________________________________________________ Office Notes, Office Memoranda of Coram, appearances, Court's orders of directions Court's or Judge's order and Registrar's orders.
Ms Babhulkar, h/f Mr. M.A. Kadu, Advocate for the appellant/s Ms Mukta Kavimandan, AGP for the respondent-State -------------------------------
CORAM
: SANDIPKUMAR C. MORE, J.
DATE : 21 st January, 2025 1.
Leave to carry out the amendment forthwith.
2.
Heard learned counsel for the appellant/ acquiring body. The State appears to be formal party. The ld counsel for ld representatives of deceased respondent No.1 claimant despite of appearance remained absent. 3.
The application is for condonation of delay of 93 days in filing appeal by the acquiring body against the judgment and award dated 19.05.2022 in Case No.1150/AMT/AMT/2018.
4.
There is no strong objection from other side. 5.
As such, considering the short period of delay, it stands condoned. The application is allowed and disposed of.
6.
The appeal be registered after removal of office nd.thawre
objection, if any.
CIVIL APPLICATION (CAF) No.2553/2022 7.
Since the appellant/acquiring body has deposited the entire amount of compensation with interest, the application is made absolute in terms of its prayer during the pendency of this appeal and according, it is disposed of.
(SANDIPKUMAR C. MORE, J.) nd.thawre