Executive Engineer, Bembla Project Division, Yavatmal v. Sudhakar Mahadeo Singane And 2 Others
2609 FA 629-2015 1/1
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR.
C.A.F. No. 3899/2017 IN FIRST APPEAL No. 629/2015 (EXE. ENGINEER, BEMBLA PROJECT DIVISION, YAVATMAL -vs- SUDHAKAR MAHADEO SINGANE AND OTHERS) ------------------------------------------------------------------------------------------------------------------------------------ Office notes, Office Memoranda of Coram, appearances, Court's orders Court's or Judge's Orders.
or directions and Registrar's orders.
Shri V.G. Palshikar, counsel for appellant.
Shri A.B. Nakshane, counsel for respondent no.1. Mrs. M.S. Naik, AGP for respondent nos.2 and 3. CORAM: S.B. SHUKRE, J.
DATE : SEPTEMBER 26, 2017.
Heard.
Perused the impugned award and the grounds taken in the appeal.
I am of the view that this application can be partly allowed and it is allowed accordingly. Respondent no.1 is permitted to withdraw 75% of the amount deposited in this Court, on his furnishing usual undertaking, within six weeks from the date of the order. Remaining amount be invested in the Fixed Deposit Account, in any nationalized bank, as per rules, till final disposal of the appeal.
Application is disposed of.
JUDGE Yenurkar