Executive Engineer, Vidarbha Irrigation Development Corporation, Nagpur v. Rajeram S/O Bapurao Kumare And Others
Order 269caf1475.19
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR C.A.F.No.1475 of 2019 in F.A.St.No.20726 of 2018 (Executive Engineer, V.I.D.C., Nagpur .vs. Rajeram s/o. Bapurao Kumare and Ors.) Office notes, Office Memoranda of Coram, appearances, Court's orders Court's or Judge's Orders or directions and Registrar's orders.
Mr.I.P.Khisti, Advocate for the appellant/applicant. Mrs.A.R.Kulkarni, A.G.P. for respondent nos. 2 and 3.
CORAM
: N. W. SAMBRE, J.
DATE : 26.9.2019.
Heard.
There is delay of 392 days. For the reasons disclosed in the application, same is allowed. Delay stands condoned.
First Appeal St.No.20726 of 2018 Heard.
Prima facie, it appears that enhanced compensation for village Mankapur @ Rs.4,35,000/- per hectare is based on the enhancement granted in adjoining village in the Land Acquisition Case. There is no consideration as regards location and other supporting evidence. That being so, Admit.
Mrs.A.R.Kulkarni, learned Assistant Government Pleader waives service for respondent nos. 2 and 3.]
Order 269caf1475.19 Paper book be filed within a period of six months.
Learned Counsel is permitted to deposit the balance amount of compensation in this Court within a period of six weeks, failing which the appeal shall stand dismissed without further reference to the Court.
To be heard along with F.A.St.No.10186 of 2018, 107232 of 2019, 20726 of 2018, 1942 of 2019 and 2761 of 2019.
JUDGE jaiswal