← Library
Bombay High CourtCAF/628/2019disposedoff

Vasantrao Marotrao Madge v. Executive Engineer, Bembla Project Division, Yavatmal And 2 Others

2019-12-13Hon'Ble Shri Justice Vinay Joshi2 pages

Order 1312caf628.19

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH, NAGPUR.

C.A.F.NO. 628/2019 IN F.A.ST. NO. 20830/2018. Vasantrao Marotrao Madge -VERSUSExecutive Engineer, Bemble Project and others. Office notes, Office Memoranda of Coram, appearances, Court'

s orders Court' s or Judge'

s Orders or directions and Registrar'

s orders.

Shri V.N. Patre, Advocate for the Applicant.

Ms. T. Udeshi, A.G.P. for Non-applicant nos. 2 and 3. CORAM : VINAY JOSHI, J.

DATE : 13.12.2019.

Heard.

2.

The applicant is seeking condonation of delay of 306 days caused in filing the First Appeal. The learned counsel for the applicant submits that in identical matters, similar quantum of delay is condoned.

3.

For the reasons stated in the application, the delay stands condoned. It is made clear that the applicant would not be entitled to interest for the period of delay. Civil Application is accordingly allowed and disposed of. No costs.

Order 1312caf628.19 ........

First Appeal No. /2019.

Heard.

2.

Admit.

Learned A.G.P. waives notice for respondent nos. 2 and 3.

JUDGE Rgd.