Dnyaneshwar Marotrao Talwekar v. The Project Director National Highways Authority Of India Project Implementation Unit Yavatmal
1 26-AA30-2023
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH : NAGPUR CIVIL APPLICATION (CAM) NO.
OF 20 IN ARBITRATION APPEAL STAMP NO. 199138 OF 2023 (DNYANESHWAR MAROTRAO TALWEKAR..VS..PROJECT DIRECTOR, NHAI & OTH.) - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Office Notes, Office Memoranda of Coram, Court's or Judge's orders appearances, Court's orders of directions and Registrar's orders - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Shri Bhushan Dafle, Adv. h/f. Shri A.R.Patil, Adv. for Applicant. Shri R.S.Sardey Advocate for Respondent Nos.1 and 2. Ms Payal Bawankule, A.G.P. for Respondent Nos. 4 and 5. CORAM : A NIL S. KILOR , J.
DATED : FEBRUARY 02 , 20 .
1.
Heard.
2.
This is an application for condonation of 4 days' delay in filing the Arbitration Appeal.
3.
For the reasons stated in the application and as the sufficient explanation has been given for causing such delay, the application is allowed. The delay is condoned. 4.
The Civil Application is disposed of accordingly. JUDGE RRaut..