Executive Engineer, Khadakpura Project,Deulgaon Mahi v. Sukhdeo Amruta Jadhav And 2 Others
1 caf3443.16
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH : NAGPUR C.A.F. NO.3443/2016 IN FIRST APPEAL NO.504/2016 Vidarbha Irrigation Development Corporation, through its Executive Engineer, Khadakpura Project, Deulgaon Mahi ..Vs..
Sukhdeo Amruta Jadhav and others - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Office Notes, Office Memoranda of Coram, Court's or Judge's orders appearances, Court's orders of directions and Registrar's orders - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - CORAM : Z.A.HAQ, J.
DATED : 25.10.2016.
Heard Shri Anoop Parihar, Advocate for the applicant/appellant.
Accepting the reasons stated in the application, the appellant is permitted to deposit the amount within two weeks. If the amount is deposited within two weeks, the interim order granted on 15th March, 2016 shall continue until further orders. The claimant is at liberty to file application seeking permission to withdraw the amount. The civil application No.3443/2016 is disposed in the above terms. No costs.
JUDGE Tambaskar.