Akola Oil Industris Ltd., Lingam Power And Infrastructure Pvt. Ltd. Hyderabad Thr. Dhantu R. Sharma v. Official Liquidator

2023-10-30Hon'Ble Smt. Justice M. S. Jawalkar2 pages

1 42 cal 07-2023

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH : NAGPUR CIVIL APPLICATION (CAL) NO.07/2023 IN OFFICIAL LIQUIDATOR REPORT (OLR) NO.04/2023 IN COMPANY PETITION NO.5/2001 Lingam Power and Infrastructure Pvt. Ltd, thr. Its representative, Shri Dantu Ramesh Sharma - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Office Notes, Office Memoranda of Coram, Court's or Judge's orders appearances, Court's orders of directions and Registrar's orders - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Shri S.V. Deshpande, Advocate for Official Liquidator Shri Anup Dhore, Advocate for applicant CORAM :

SMT. M.S. JAWALKAR, J.

DATED :

30/10/ The present application is filed by highest bidder in respect of Venkateshwara Edusupport Ltd. This Court vide order dated 27/07/2023 granted one month time to deposit the amount i.e. Rs.3,49,08,000/- being highest bidder. By this application, the applicant is seeking further three months time to deposit the amount.

2.

In my considered opinion, there is no attempts made to deposit any part of the said payment. As such, time as prayed for, can be extended only subject to condition that the applicant should deposit 25% of total amount

2 42 cal 07-2023 of bid. Accordingly, application is allowed.

3.

The time is extended by another three months subject to deposit 25% of total amount of bid within a period of two weeks.

4.

The application stands disposed of accordingly.

JUDGE R.S. Sahare