← Library
Bombay High CourtCAF/3922/2023disposed off

V. I. D. C. Through Executive Engineer, Minor Irrigation Division, Washim And Another v. Arun Sitaram Pawar And 2 Others

2024-01-03Hon'Ble Shri Justice Anil L. Pansare2 pages

38-CAF-3922-2023

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH, NAGPUR.

CIVIL APPLICATION (F) NO. 3922 OF 2023 IN FIRST APPEAL NO. 252 OF 2021 (Vidarbha Irrigation Development Corporation, through its Executive Engineer Vs. Arun Sitaram Pawar & Ors.) __________________________________________________________________________ Office Notes, Office Memoranda of Coram, appearances, Court'

s orders of directions Court'

s or Judge'

s orders.

and Registrar'

s Orders.

Ms Anjali Agrawal h/f Shri H.D. Marathe, Counsel for the appellant.

Shri Pavan Sarise h/f Shri R.J. Shinde, Counsel for the applicant/respondent no.1.

Ms H.S. Dhande, A.G.P. for respondent nos. 2 and 3. .....

CORAM : ANIL L. PANSARE, J.

JANUARY 3, 2024.

By this application, the applicant/ respondent no.1 - claimant seeks permission to withdraw 25% balance amount of compensation deposited by the appellant.

2] Perused the impugned judgment.

Considering the nature of evidence on record, the claimant is permitted to withdraw 25% balance amount of compensation on filing an undertaking that in case the appeal is allowed, the said amount shall be repaid with interest at such rate the Court may direct and further the claimant shall furnish solvent surety to the extent of remaining amount which is allowed to be withdrawn to the satisfaction of the Registrar (Judicial). 3] The Civil Application is disposed of.

38-CAF-3922-2023 FIRST APPEAL NO. 252/2021 4] Issue notice to the respondents returnable in two weeks.

5] Shri Pavan Sarise h/f Shri R.J. Shinde, learned Counsel waives notice for respondent no.1. 6] The learned A.G.P. waives notice for respondent nos. 2 and 3.

7] The parties are put to notice that the appeal may be taken-up for final hearing at the stage of admission. The parties are at liberty to file compilation of documents which they intend to rely upon.

8] In the meantime, call R & P.

(ANIL L. PANSARE, J.) Sumit