The Executive Engineer, Bembla Project Division No.5, Yavatmal v. Shriram Natthu Kale And 2 Others
FA 1115-16 1/2
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR.
C.A.F. No. 3619/2016 IN FIRST APPEAL NO. 1115/2016 THE EXE. ENGINEER, BEMBLA PROJECT DIVISION NO.5, YAVATMAL, DISTT. YAVATMAL -vsSHRIRAM NATTHU KALE AND OTHERS. ------------------------------------------------------------------------------------------------------------------------------------ Office notes, Office Memoranda of Coram, appearances, Court's orders Court's or Judge's Orders.
or directions and Registrar's orders.
Shri A.M. Gupta, Adv. H/F Shri P.B. Patil, counsel for appellant.
Shri P.V. Shendre, Adv. H/F Shri R.D. Hajare, counsel for respondent no.1.
Ms. S. Haider, AGP for respondent nos.2 and 3. CORAM : DR S.S.PHANSALKAR-JOSHI, J.
DATE : JUNE 09, 2017 As per the office note, notice issued to respondent no.1 is still awaited. However, learned counsel Mr. P.V. Shendre appears for the respondent no.1 in appeal.
Heard learned counsel for the appellant, learned counsel for the respondent no.1 and learned AGP for the respondent nos.2 and 3.
As the entire amount of compensation is deposited within the stipulated period, order of stay granted earlier is hereby confirmed, continued and made absolute till the decision of appeal.
Application is accordingly disposed of finally. FIRST APPEAL No. 1115/2016.
On the request of the learned counsel for the
FA 1115-16 2/2 appellant, time of 4 weeks is granted as a last chance for filing the private paper book.
JUDGE Yenurkar