V. I. D. C. Through Executive Engineer, Lower Project Division, Yavatmal v. Rameshwar Kisnaji Borkute And 2 Others
17caf634.2020.
1/2
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR Civil Application (F) No.634/2020 in First Appeal st No.22422/2019 V.I.D.C. thr. Executive Engineer, Yavatmal Project Lower Division, Yavatmal. Vs Rameshwar Kisnaji Borkute and others.
******************************************************************************************************************* Office notes, Office Memoranda of Coram, appearances, Court'
s orders Court's or Judge's Orders or directions and Registrar's orders.
******************************************************************************************************************* Shri H.D. Marathe, Advocate for appellant.
Shri M.A. Kadu, AGP for Respondent Nos. 2 and 3. CORAM : S.M. MODAK, J.
DATE : 25 th JUNE, 2021.
Hearing was conducted through Video Conferencing and the learned Counsel agreed that the audio and visual quality was proper.
There is a delay of 714 days in preferring an appeal. 2.
Issue notice to the respondents, returnable after ten weeks.
3.
Learned AGP Shri M.A. Kadu, waives notice for the respondent Nos.2 and 3.
Civil Application (CAF) No.635/2020 Heard both the sides.
Stay is granted to the execution of the impugned judgment and decree subject to deposit of entire decretal amount within the period of 12 weeks.
17caf634.2020.
2/2 Application is disposed of.
The claimant is at liberty to ask for its withdrawal and it will be considered on merits.
JUDGE rkn