The Executive Engineer, Lower Wardha Project Division, Vidc Wardha v. Nagorao Mahadeo Atram, And 2 Others
caf.3481.15 1/1 I N THE HIGH COURT OF JUDICATURE AT BOMBAY NAGPUR BENCH, NAGPUR Civil Application [CAF] No.3481 of 2015 in First Appeal No.594 of 2015 (The Executive Engineer, Lower Wardha Project Division, Wardha vs.
Nagorao Mahadeo Atram and others) =-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-= Office notes, Office Memoranda of Coram, appearances, Court's orders Court's or Judge's Orders or directions and Registrar's orders.
=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-= Shri A.R. Ingole, , Advocate for the Applicant-Respondent No.1. Shri S.G. Jagtap, Advocate for the Appellant. Shri N.S. Khubhalkar, A.G.P. for Respondent Nos.2 and 3. CORAM : R.K. DESHPANDE, J.
DATE : DECEMBER 18, 2015.
The claimant-respondent No.1 is permitted to withdraw 50% of the amount deposited by the appellant in this Court upon furnishing solvent security to the satisfaction of the Registrar (Judicial) of this Court.
The civil application is partly allowed and disposed of as such.
JUDGE *sandesh