The Executive Engineer, Nagpur Medium Project, Nagpur Division, V.I.D.C. Nagpur v. Shri Gulabrao Maroti Nimbulkar And 2 Others
IN THE HIGH COURT OF JUDICATURE AT BOMBAY:
NAGPUR BENCH : NAGPUR Civil Application [CAF] No. 3872 of 2016 IN First Appeal No. 1012 of 2016 [Executive Engineer, Nagpur Medium Project, Nagpur Division, VIDC, Ngp. Vs. Gulabrao Maroti Nimbulkar & others] Office Notes, Office Memoranda of Coram, appearances, Court's orders Court's or Judge's orders or directions and Registrar's orders.
Mr. P.B. Patil, Adv., for the applicant.
Mr. C.R. Najbile, Adv., for respondent no.1.
Mr. Ekre, AGP for respondent nos. 2 and 3.
----
CORAM
:
A. S. CHANDURKAR, J.
DATE :
08th March, 2017 If the amount of compensation is deposited in this Court within a period of four weeks from today, the execution of the impugned Award shall remain stayed during pendency of the Appeal. If the amount is not so deposited, the claimant would be at liberty to execute the Award.
Civil Application is disposed of.
Judge |hedau|