V.I.D.C. Through Its Executive Engineer, Bembla Project, Yavatmal v. Pundlik S/O Sadu Ambhore (Dead) Through Lrs. Manorama Wd/O Pundlik Ambhore And Others
22fa466.20210.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH : NAGPUR MISC. CIVIL APPLICATION NOS. 02, 03 AND 01 OF 2026 IN CIVIL APPLICATION NO. 240 OF 2023 IN FIRST APPEAL NO. 466 OF 2010 VIDC, Bemble Project Vs Pundlik Sadu Ambhore since dead through his legal representatives Manorama Pundlik Ambhore and others.
Office Notes, Office Memoranda of Court's or Judge's Order Coram, appearances, Court's Orders or directions and Registrar's order Mr. A.B. Patil, counsel for applicant/appellant. Ms. Deepa Charlewar, AGP for respondent Nos. 2 and 3.
CORAM
: PRAVIN S. PATIL, J.
DATE : 05/01/2026 1.
Heard.
2.
By these applications, applicant is seeking condonation of delay of 770 days caused in filing the revision application, as well as restoration of the civil application, with permission to carry out the necessary compliance in the matter and to remove the office objections. 3.
The applicant has given specific reasons in the application, particularly in paragraphs Nos. 3 to 5. The said averments have not been controverted in the matter. Hence, for the reasons stated in the application, civil applications are allowed.
4.
The order passed by Registrar (Judicial) dated 29/08/2023 is hereby quashed and set aside.
rkn
22fa466.20210.odt 5.
The applicant/appellant is permitted to do the compliance in the matter and remove the office objections within a period of two weeks. 6.
List the matter after removal of all the office objections. (PRAVIN S. PATIL, J.) rkn