Executive Engineer, (V.I.D.C.) Bembla Project Division, Yavatmal v. Sudhatai Jiwanrao Sthool And Others
1 caf1391.17.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH AT NAGPUR CAF NO.1391/2017 IN FIRST APPEAL ST. NO.25194/2016 [Executive Engineer, VIDC, Bembla Project Division, Yavatmal .vs. Sudhatai Jiwanrao Sthool and others] - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Office Notes, Office Memoranda of Coram, Court's or Judge's orders appearances, Court's orders of directions and Registrar's orders - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Mrs. U.A. Patil h/f Shri V.G. Palshikar, Advocate for applicant, Mrs. H.N. Prabhu, AGP for respondent nos.2 and 3. ..........
CORAM : KUM. INDIRA JAIN, J.
DATED : SEPTEMBER 26, 2017.
Heard.
It is submitted that the entire amount has been deposited on 6.9.2017.
In view of the reasons assigned in the application, delay is condoned.
Civil Application stands disposed of.
FIRST APPEAL ST. NO.25194/2016 AND CIVIL APPLICATION NO.1392/2017 Heard.
Notice before admission to the respondents, returnable within four weeks.
Learned AGP Mrs. Prabhu waives notice for respondent nos.2 and 3.
As the entire amount has been deposited, stay to the execution and operation of the impugned judgment and award dated 15.9.2015 passed by the Joint Civil Judge, Senior Division, Yavatmal in LAC No.541/2006, during pendency of appeal.
JUDGE Gulande