Union Of India, Central Railway Through Deputy Chief Engineer (Construction) v. Sau. Rekha Narhari Bind And Others
2024:BHC-NAG:5566 1 18.caf.1185.2024
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR.
CIVIL APPLICATION (CAF) NO. 1185 OF 2024 IN FIRST APPEAL NO. 1273 OF 2013 Union of India VS.
Sau Rekha Narhari Bind and others _______________________________________________________________ Office Notes, Office Memoranda of Coram, appearances, Court's orders of directions Court's or Judge's orders.
and Registrar's Orders.
None for the appellant Mr D. P. Dapurkar, Advocate for respondent No.1 Ms Sonia Thakur, AGP for respondent Nos. 2 and 3/State CORAM :
G.A. SANAP, J.
DATE :
MAY 8, 2024.
Heard.
2.
This is an application, in a disposed of appeal, made by respondent No. 1 for withdrawal of compensation amount alongwith accrued interest.
3.
In view of the facts stated in the application, the application is allowed.
4. The respondent No. 1 is allowed to withdraw the amount of compensation with accrued interest. 5.
The civil application stands disposed of, accordingly.
2 18.caf.1185.2024 CIVIL APPLICATION NO. 2421 OF 2021 6.
Call the report of Nazir as to the amount of the accrued interest as well as the deposit of the accrued interest. 7.
Stand over after summer vacation 2024.
(G. A. SANAP, J.) Namrata