The Executive Engineer, Khadakpurna Project Division, Vidc Deulgaon Raja Dist Buldana v. Madhukar Pundalik Dandale And Others
fa.440.16 1
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR Civil Application [CAF] No.4071 of 2016 in First Appeal No.440 of 2016 (Executive Engineer, Khadakpurna Project Division, V.I.D.C., Buldana vs.
Madhukar Pundalik Dandale and others) =-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-= Office notes, Office Memoranda of Coram, appearances, Court's orders Court's or Judge's Orders or directions and Registrar's orders.
=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-= Shri K.S. Narwade, Advocate for the Applicant/Respondent No.1. Shri S.S. Godbole, Advocate for the Appellant. Shri N.R. Rode, A.G.P. for Respondent Nos.2 and 3.
CORAM
: S.B. SHUKRE, J.
DATE : 21 st DECEMBER, 2016.
Heard.
Having considered the reasons given in the impugned judgment and order, I am of the view that this application can be conditionally allowed.
The application is allowed. Respondent No.1claimant is permitted to withdraw 75% of the amount deposited in this Court against usual undertaking and remaining 25% of the deposited amount against solvent surety both to the satisfaction of the learned Registrar (Judicial) to be furnished within four weeks from the date of the order.
The application is disposed of accordingly.
*sdw JUDGE