Chandrabhabai W/O Mahadeo Alhat v. The Executive Engineer, Man Project Division Khamgaon And 2 Others
IN THE HIGH COURT OF JUDICATURE AT BOMBAY:
NAGPUR BENCH : NAGPUR Civil Application [CAO] No. 90 of 2017 IN Cross-Appeal no. 3519 of 2015 IN First Appeal No. 952 of 2012 [Executive Engineer, Man Project Division, Khamgaon, Buldana Vs. Smt. Chandrabhagabai Mahadeo Alhat & others] Office Notes, Office Memoranda of Coram, appearances, Court's orders Court's or Judge's orders or directions and Registrar's orders.
Mr. A. B. Kale, Adv., for the applicant-respondent no.1. Mr. P.B. Patil, Adv., for respondent no.1.
Mrs. Kulkarni, AGP for respondent nos. 2 and 3. ----
CORAM
:
A. S. CHANDURKAR, J.
DATE :
31st January, 2017 Prayer is to condone delay in filing the Crossobjection. Reasons for the delay are mentioned in paras 1 and 2 of the application. It is stated that the applicant did not receive the amount of compensation as enhanced by the Reference Court and hence she was not in a position to file the Cross-objection earlier. There is no reply filed to the application so as to oppose the prayer made therein.
In view of aforesaid, the delay in filing the Cross-
Objection is condoned, subject to applicant not being entitled for interest on the amount of compensation, if enhanced, from 13th April, 2010 till 12th February, 2015. Civil Application is allowed and disposed of. ---- Cross-Objection St. No. 3519/15 :
Heard.
Admit.
Shri P.B. Patil, learned counsel, waives notice on behalf of the respondent no.1, and Smt. Kulkarni, learned Asstt. Govt. Pleader, for respondent nos. 2 and 3.
In view of order passed on Civil Application No. 90 of 2017, the appellant will not be entitled for interest on the amount of compensation, if enhanced, from 13th April, 2010 till 12th February, 2015.
Judge |hedau|