← Library
Bombay High CourtCAO/193/2020allowed

Vidarbha Irrigation Devp. Corporation, Thr. Executive Engineer, Yavatmal Project Construction Div. v. Bebitai Ramchandra Bansod And Others

2021-01-07Hon'Ble Shri Justice S.M. Modak2 pages

MCA St.25215.2019.

1/2

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH, NAGPUR Civil Application (CAO) No.193 of 2020 IN Miscellaneous Civil Application Stamp No.25215 of 2019 IN First Appeal No.1407 of 2017(D) Vidarbha Irrigation Development Corporation thr. Executive Engineer Vs. Bebitai Ramchandra Bansod & Others =-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-= Office notes, Office Memoranda of Coram, appearances, Court'

s orders Court's or Judge's Orders or directions and Registrar's orders.

=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-= Ms. Utkarsha Vaidya, Advocate h/f Mrs. Ira P. Khisti, Advocate for the Appellant. Shri M.A. Kadu, A.G.P. for Respondent Nos.2 and 3. CORAM : S.M. MODAK, J.

DATE : 7 th JANUARY, 2021.

Heard both the sides.

2.

The first appeal came to be dismissed for not filing the private paper-book within time. Now, the appellant is ready with the private paper-book.

3.

Hence, there is delay of 257 days in filing restoration application. The reasons are convincing in both the applications. Hence the order:-

O R D E R

i.

Both applications are allowed.

ii. The delay caused in filing restoration application is condoned subject to filing the private paper-book within a period of two weeks.

MCA St.25215.2019.

2/2 iii. The First Appeal No.1407/2017 is restored. iv.Both civil applications are disposed of.

JUDGE vijay