The New India Assurance Co. Ltd., Gondia Thr. Branch Manager v. Rajkumar S/O Shrawan Kshirsagar And Others
1 / 2 1.CA293.2025A
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH : NAGPUR CIVIL APPLICATION (CAF) NO. 293 OF 2025 IN FIRST APPEAL (ST) NO. 25339 OF 2024 The New India Assurance Company Ltd., Gondia Vs.
Rajkumar s/o Shrawan Kshirsagar and Ors.
---------------------------------------------------------------------------------------------- Office notes, Office Memoranda of Coram, appearances, Court's orders Court's or Judge's Orders.
or directions and Registrar's orders.
---------------------------------------------------------------------------------------------- Ms. S.H. Bhatia, Advocate for applicant.
CORAM : ROHIT W. JOSHI, J.
DATE : 03.02.2025.
There is a delay of 3 days in filing appeal under Section 173 of the Motor Vehicles Act, 1988. 2.
For the reasons mentioned in the application which are supported by affirmation the delay is condoned.
3.
The civil application is allowed.
4.
Appeal be registered and put up for final hearing.
First Appeal (ST) No.25339/2024 Issue notice to the respondents, returnable in four weeks.
Prity
2 / 2 1.CA293.2025A 2.
Notice to indicate that the appeal may be heard finally at the admission stage.
3.
Call for record and proceedings.
Civil Application (CAF) No. 294/2025 The learned counsel for the appellant makes a statement that the execution proceedings is filed by the respondent Nos.1 & 2/original petitioners. He makes a statement that the entire amount as awarded by the learned Tribunal will be deposited with this Court within a period of four weeks from today i.e. on or before 24.02.2025. Subject to said deposit, the execution of the impugned award is stayed till the returnable date. (ROHIT W. JOSHI, J.) Prity