V.I.D.C., Thr Its Executive Engineer, Minor Irrigation Department, Buldhana v. Gulabrao S/O Sampat Wakudkar And Others
917 caf1382.25.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR.
CIVIL APPLICATION(CAF) NO.1382 OF 2025 IN FIRST APPEAL STAMP NO.25407 OF 2024 VIDC through its Executive Engineer, Minor Irrigation Department, Buldhana Vs.
Gulabrao S/o Sampat Wakudkar & Ors __________________________________________________________________ Office Notes, Office Memoranda of Coram, appearances, Court's orders of directions Court's or Judge's orders.
and Registrar's Orders.
Shri S.K. Bhoyar, Advocate for applicant.
Shri K.J. Tople, Advocate for respondent nos.1&2. Shri H.D. Dubey, AGP for respondent/State.
CORAM : M.W. CHANDWANI, J.
DATE : 18.09.2025.
1.
By this application, the applicant is seeking condonation of delay of 55 days in filing the appeal. 2.
Considering the period of delay i.e. 55 days, within permissible limit of 60 days and for the reasons mentioned in application coupled with no objection of the respondents, delay is condoned. Appeal be registered.
3.
The application stands disposed of.
FIRST APPEAL STAMP NO.25407 OF 2024 4.
Since the appellant has already deposited the amount of award, there shall be stay to the execution of impugned award, during pendency of the appeal.
917 caf1382.25.odt 5.
Learned counsel for the appellant seeks time to file reply to the application for withdrawal of amount. 6.
Stand over to 03.10.2025.
JUDGE Wagh