Exe. Engineer, Vidarbha Hydro Proj. Electric And Lift Irrigation, Bhandara Div. And Another v. Shri Harichandra Daulat Motghare (Died) And Others
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR.
CIVIL APPLICATION (CAF) NO. 1088/2019 IN FIRST APPEAL (ST) NO. 28121/2018 Executive Engineer, Vidarbha Hydro Project Electric & Lift Irrigation, Bhandara & anr. -VERSUSHair Chandra Daulat Motghare & ors.
Office notes, Office Memoranda of Coram, appearances, Court'
s orders Court's or Judge's Orders or directions and Registrar'
s orders.
Mrs. U. A. Patil, Advocate for appellants/applicants. Shri S. W. Sambre, Advocate for respondent Nos. 2 and 3. CORAM : SMT. ANUJA PRABHUDESSAI, J.
DATE : 25.01. 2021.
By this application, the applicants have sought to condone the delay of 46 days in challenging the judgment and award dated 16.08.2018 in Employees Compensation Case No. 113/2011.
2.
For the reasons stated in the application, which in my considered view constitute sufficient grounds, the delay is condoned.
3.
Application stands disposed of.
CIVIL APPLICATION (CAF) NO. 1089/2019 4.
The applicants have sought stay of the execution and implementation of the impugned judgment and award dated 16.08.2018.
5.
Learned counsel for the appellants states that amount of Rs. 6,08,768/- has been deposited before the Labour Court. It is also stated that respondent No. 4 has deposited amount of Rs. 6,00,000/- approximately. In the light of the said statements, the execution and implementation of the impugned judgment and award is stayed till final disposal of the appeal.
6.
Application stands disposed of.
FIRST APPEAL (ST) NO. 28121/2018 7.
Heard.
8.
Admit, 9.
Learned counsel for respondents waive
service of notice.
10.
Call for record and proceedings.
11.
Paper book be filed within a period of six months.
(SMT. ANUJA PRABHUDESSAI, J.) Gohane.