Vidc Thr. Exe. Engineer, Nimna Painganga Proj. Division, Yavatmal (Earlier-Bembla Canal Proj. Div.) v. Tukaram Dadaji Gadekar And Others
22 CAF-4105-2019
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR.
CIVIL APPLICATION (F) NO.4105 OF 2019 IN FIRST APPEAL ST. NO.28804 OF 2018 [Vidarbha Irrigation Development Corporation ..Vrs.. Tukaram Dadaji Gadekar and Ors.] _______________________________________________________________________________________ Office Notes, Office Memoranda of Coram, appearanfices, Court's orders of direfictions Court's or Judge's order and Registrar's orders.
Ms. A. S. Athalye, Advoficate for Applificant/Appellant Shri. A. R. Ingole, Advoficate for Respondent No.1 Ms. H. N. Jaipurkar, AGP for Respondent Nos.2 and 3. CORAM :
NITIN W. SAMBRE, J.
DATE :
st SEPTEMBER, 2021.
Heard.
2.
For the reasons disficlosed in the Applification, the Applification is allowed and is disposed of. The delay of 101 days ficaused in fling the Appeal, is ficondoned. FIRST APPEAL ST NO.28804 OF 2018 3.
Heard.
4.
Shri. A. R. Ingole, learned Counsel waives for Respondent No.1.
5.
Ms. H. N. Jaipurkar, learned Assistant Government Pleader waives for Respondent Nos.2 and 3.
6.
To be heard with First Appeal St. No.22415 of 2019.
CIVIL APPLICATION (F) NO.4106 OF 2019 7.
Heard.
8.
The Applification is allowed, in terms of prayer
22 CAF-4105-2019 Clause (i) as the entire amount of ficompensation is deposited.
CIVIL APPLICATION (F) NO.1868 OF 2021 9.
Respondent/Land Owner is permitted to withdraw an amount of ficompensation to the extent of 75% with aficficrued interest thereon upon furnishing mutual undertaking.