← Library
Bombay High CourtMCA/360/2018delay condoned

Aum C And F Agency Pvt. Ltd., Thr. Its Managing Director, Rajendra Devisingh Shekhawat And ANR., v. Karl Logistics And 6 ORS.,

2018-08-27Hon'Ble Shri Justice N. M. Jamdar,Hon'Ble Shri Justice Prithviraj K. Chavan1 pages

Amrut 1 MCA360-18dt 27-08-2018 IN THE HIGH COURT OF BOMBAY AT GOA MISC. CIVIL APPLICATION NO.360 OF 2018 IN STAMP NUMBER MAIN NO.40 OF 2018 M/s. Aum C and F Agency Pvt. Ltd. & Anr.

...

Applicants

Versus

M/s. Karl Logistics & Ors.

.... Respondents Mr. S. G. Desai, Senior Advocate with Ms. S. Shelke, Advocate for the Applicants.

Mr. J. A. Lobo, Advocate for Respondent Nos.2 & 4. Coram : N.M. Jamdar & Prithviraj K. Chavan, JJ.

Date : 27 August 2018.

P.C.:

Notice was issued in this application and the Respondents were served. The delay in filing the appeal is of 33 days. Perused the application. Sufficient cause is made out. The delay is condoned. The Civil Application is allowed in terms of prayer clause (a). 2.

Place the appeal on board for admission on 17 September 2018.

Prithviraj K. Chavan, J. N.M. Jamdar, J.