IN THE HIGH COURT OF BOMBAY AT GOA

MISC.CIVIL APPLICATION NO. 253 OF 2019 IN WRIT PETITION NO. 1091 OF 2018 MALHAN CONSTRUCTIONS PVT. LTD., REP. BY ITS DIRECTOR, RAJIV MALHAN., ... Applicant

Versus

SHASHIKANT MALU PANKAR AND ANR., ... Respondents Ms. T. Mashelkar, Advocate for the Petitioners. Coram:- C. V. BHADANG, J.

Date:- 7th March 2019 P.C.

This is an application for substituted service on the respondent nos.1 and 2 which is supported by an affidavit.

2. For the reasons mentioned in the application, the same is allowed. The returnable date in the notice shall be shown as 18.04.2019.

3. Civil Application is disposed off.

C. V. BHADANG, J.

arp/*