Elecon Construction Pvt. Ltd., Thr. Its Aut. Director Mr. Joseph Mathew., v. Mr. Dharmendra Sharma And 2 ORS.,
IN THE HIGH COURT OF BOMBAY AT GOA
CONTEMPT PETITION NO. 15 OF 2017 IN WRIT PETITION NO. 1127 OF 2016 ELECON CONSTRUCTION PVT. LTD., THR. ITS AUT. DIRECTOR MR. JOSEPH MATHEW., ... Petitioner
Versus
MR. DHARMENDRA SHARMA AND 2 ORS., ... Respondents Mr. Vivek Angelo Rodrigues, Advocate for the petitioner. Mr. Dattaprasad Lawande, Advocate General with Ms. P. Bhandari, Addl. Government Advocate for the respondents. Coram:- F. M. REIS & PRITHVIRAJ K. CHAVAN, JJ.
Date:- 19th June, 2017 P.C.
Mr. V. Rodrigues, learned counsel appearing for the petitioner points out that the subject amount has already been paid by the respondents. Hence, the learned counsel seeks leave to withdraw the above Contempt Petition. The Contempt Petition stands accordingly dismissed as withdrawn.
PRITHVIRAJ K. CHAVAN, J.
F. M. REIS, J.