Cholamandalam Ms General Insurance Company Ltd., Thr. Legal Manager Hemant B Gaokar v. Priyanka K Mayekar And 5 ORS
202-MCA-148-22.DOC Santosh
IN THE HIGH COURT OF BOMBAY AT GOA
MISC. CIVIL APPLICATION NO. 148 OF 2022 IN FIRST APPEAL NO.813 OF 2022 (F) CHOLAMANDALAM MS GENERAL INSURANCE COMPANY LTD., THR.
LEGAL MANAGER HEMANT B GAOKAR .... APPLICANT Versus.
PRIYANKA K MAYEKAR AND 5 ORS ... RESPONDENTS. Mr. James Lopes, Advocate for the Applicant. Mr. M. D'Souza, Advocate for Respondents No.1 to 4. Mr. P. Vaze, Advocate for the Respondent No.5. Mr. Jeevan Bandekar, Advocate for Respondent No.6. CORAM :
M. S. SONAK, J.
DATE :
th August 2022 P.C. : - 1.
Heard the learned Counsel for the parties.
2.
There is a delay of 48 days in instituting the appeal. The delay has been sufficiently explained. The applicant is entitled to the benefit of the order made by the Hon'ble Supreme Court of th August 2022
202-MCA-148-22.DOC India extending the period of limitation during the COVID pandemic.
3.
Therefore, considering the above aspects, the delay is condoned subject to payment of 5,000/- by way of costs payable ₹ to the claimants. The costs should be paid/deposited on or before th August 2022, without fail and without seeking any extension of time. Further, if the costs are not paid by 24th August, then this application shall be deemed to be dismissed.
4.
Civil application is disposed of in the above terms. M. S. SONAK, J.
th August 2022