Royal Power Turnkey Implements Pvt. Ltd. And ANR., v. Nanu Industiries, Thr. Its Partners, Pravas Krishna Naik.,
IN THE HIGH COURT OF BOMBAY AT GOA
APPEAL UNDER ARBITRATION ACT NO. 20 OF 2018 ROYAL POWER TURNKEY IMPLEMENTS PVT. LTD. AND ANR., ... Appellants
Versus
NANU INDUSTIRIES, THR. ITS PARTNERS, PRAVAS KRISHNA NAIK., ... Respondent Mr. Clayton Anthony Fonseca, Advocate for the Appellant. Mr. M. D'Souza, Advocate for the Respondents. Coram:- C. V. BHADANG, J.
Date:- 24th April 2019 P.C.
The parties have reached an amicable settlement and the Consent Terms are drawn which are placed on record and marked 'X' for identification. The same are signed by the parties and their respective Advocates. They admit the correctness of the contents.
2. As per the terms agreed, the respondent to withdraw the cases as set out in para 2 of the Consent Terms while the appellant shall withdraw the Criminal Revision Application as set out in para 3 of the Consent Terms.
3. In such circumstances, the learned Counsel for the parties
AUA/20/2018 pray for disposal of the appeal in view of the Consent Terms.
4. In such circumstances, the AUA is disposed off in view of the Consent Terms, with no order as to costs. C. V. BHADANG, J.
arp/*