Prajal Sakhardande And ANR v. State Of Goa Thr. Its Chief Secretary And 6 ORS
Santosh
IN THE HIGH COURT OF BOMBAY AT GOA
PIL WRIT PETITION NO.22 OF 2024 PRAJAL SAKHARDANDE AND ANR. .... PETITIONERS.
Versus
STATE OF GOA, THR. THE CHIEF SECRETARY AND ANR. .... RESPONDENTS. Mr Hrudaynath S. Shirodkar, Advocate for the Petitioners. Mr D.J. Pangam, Advocate General with Mr P. Arolkar, Addl. Govt. Advocate the Respondents No.1 to 4, 5 & 6 Correction carried out as per order dated 6/5/2024 in MCA No.1147/24(F) CORAM :
M. S. SONAK & VALMIKI MENEZES, JJ.
DATED :
23rd April 2024.
P.C.:
1.
Mr Shirodkar for the Petitioner. Learned Advocate General appears along with Mr P. Arolkar, learned Addl. Govt. Advocate for Respondents No.1 to 4.
2.
At the very outset, the learned Advocate General makes it clear that no trees have been cut without any permissions under the Goa Preservation of Trees Act, 1984, and there is no intention to cut any trees without following the due process of law and obtaining necessary permissions.
3.
Further, the learned Advocate General submitted that in the context of the Smart City project at Panaji, applications were
received from the user agency for the felling of the following six trees :
Tree No.
Species Girth (cm) Height (m) Landmark Mango 2.10 9.00 Near fire dept.
Rain tree A Rain Tree B 5.40 3.05 15.00 4.00 Near Zakis 3.
Mango 3.10 11.00 Near Xero.
4.
5.
6.
Mango Banyan tree Rain tree 2.50 13.00 5.02 10.00 12.00 15.00 Near Sheetal 4.
Upon receipt of the applications, the Authorities inspected each of the six trees. Te first four trees were found within the Right of Way (RoW). However, the inspection also revealed that they were not leaning or posing any danger. Terefore, the user agency was advised to take adequate measures to save the trees. Even the user agency agreed with this suggestion, and accordingly, no permission was granted to fell the first four trees referred to above. 5.
Regarding the fifth tree (Banyan tree), the inspection revealed that it was affected by the drain system, and one major trunk was leaning towards an adjoining building. Te inspection also revealed that there was no space available for the tree to grow further, as it was found congested within the RoW. Te Authorities concluded that the tree was vulnerable for all these reasons and could even be uprooted at any time. Still, considering the religious and heritage value of the tree, the user agency was apprised that translocation of this tree would be appropriate in the circumstances.
6.
Te Joint Inspection Report placed before us records that the user agency informed the Authorities that they have machinery and labour available for translocation, and translocation was possible at Campal ground, which is also government land, was chosen for translocation. Accordingly, permissions were granted to translocate the Fifth Tree (Banyan tree) to Campal ground. 7.
Te learned Advocate General states that this tree has already been translocated at the Campal ground pursuant to this permission. Mr Shirodkar made some submissions that this was not a proper translocation. However, as filed, the Petition is bereft of proper averments or suggestions for successful translocation. 8.
Regarding the sixth tree (Rain tree), the inspection report revealed that it was found leaning towards the PWD quarters and standing in a ruinous state, posing a danger to vehicular traffic, the public and pedestrians. Accordingly, the joint inspection report opined that this sixth tree needs to be cut and removed urgently. Te Tree Authority, accordingly, granted permission for the felling of this raintree. Te learned Advocate General states that the rain tree has already been removed pursuant to this permission. 9.
Tis Petition has alleged that the trees were being felled without permission from the prescribed authorities. Tis premise was not substantiated in the Petition. Merely stating that these two trees were not marked is not sufficient. In any case, the Joint Inspection Report and the permissions granted for the felling of only one tree out of six applied for by the user agency clarify the
position to some extent. One of these trees was permitted to be translocated.
10.
If the Petitioner has any grievances about the translocation order, perhaps it would still be open to the Petitioner to appeal the same before the Appellate Authority. In any case, it is open to the Petitioner to offer expert advice or suggestions so that the translocation is a success. If such suggestions are offered, we see no reason why the Authorities, who should also be interested in successful translocation, should not consider them so that the translocation project is a success. Te apprehension about the felling of trees without permission stands allayed with the learned AG's statement made at the very outset.
11.
For all the above reasons, we dispose of this Petition. 12.
Tere shall be no order for costs.
VALMIKI MENEZES, J. M. S. SONAK, J.