Bombay High CourtCRA/21/2024allowed

Shubhada L. Kundaikar v. Goa State Infrastructure Development Corporation Ltd., Thr Managing Director And 2 ORS.

2024-10-24Hon'Ble Shri Justice Bharat P. Deshpande1 pages

2024:BHC-GOA:1861 CRA 21 of 2024 Esha

IN THE HIGH COURT OF BOMBAY AT GOA

CIVIL REVISION APPLICATION NO.21 OF 2024 IN CIVIL REVISION APPLICATION NO.2356 OF 2023 (F) SHUBHADA L. KUNDAIKAR ... APPLICANT

Versus

GOA STATE INFRASTRUCTURE DEVELOPMENT CORPORATION LTD., THR MANAGING DIRECTOR AND 2 ORS.

... RESPONDENTS Mr. Ajit Kantak with Mr. Raunak Kantak, Advocates for Applicant. CORAM:- BHARAT P. DESHPANDE, J.

DATED :- 24th October, 2024 P.C.

Mr. Kantak submits that the office objections were raised in the main matter, however, there was some delay in approaching the Registry, which was not deliberate. He submits that all the objections are already cleared except the objection regarding the paper size. He undertakes to clear the objection with regard to the A4 paper size also within two weeks.

2. Accordingly, the Revision stands allowed. The impugned order dated 12.04.2024 passed by the Registrar (Judicial) is quashed and set aside. The learned Counsel for the Applicant shall clear the office objection with regard to the paper size within two weeks from today. BHARAT P. DESHPANDE, J.

Signed by: ESHA SAINATH VAIGANKAR Designation: Personal Assistant Date: 25/10/2024 14:48:24 24th October, 2024