Ignatius J. R. Fernandes And ANR., v. Shiva Puti Shirodkar And 3 ORS.,
IN THE HIGH COURT OF BOMBAY AT GOA
CONTEMPT PETITION NO. 41 OF 2018 IN SECOND APPEAL NO. 108 OF 2010 IGNATIUS J. R. FERNANDES AND ANR., ... Petitioners
Versus
SHIVA PUTI SHIRODKAR AND 3 ORS., ... Respondents Shri V.R. Tamba, Advocate for the applicants. Shri J.P. Mulgaonkar, Advocate for the respondents No.1 to 6. Coram:- NUTAN D. SARDESSAI, J.
Date:- 22nd February 2019 P.C.:
Since it is alleged that the construction activity has been undertaken as depicted in the photographs which is beyond the mundkarial area of 361 sq.mts. and taking into consideration the order dated 28/03/2011, it would be appropriate that the matter is remitted to the Trial Court for conducting an enquiry and submitting its report within three months.
2. In view thereof, the matter is remitted to the Trial Court to hold an enquiry and conclude the same within a period of six months from the receipt of the order.
3. In view thereof, the application stands disposed off. NUTAN D. SARDESSAI, J.
CP/41/2018 mv