Santosh Y. Dicholkar. v. The Executive Engineer, Works Division Vi, Gtidc, Bicholim And ANR.,
IN THE HIGH COURT OF BOMBAY AT GOA
MISC.CIVIL APPLICATION NO. 675 OF 2019 IN FIRST APPEAL NO. 102 OF 2015 SANTOSH Y. DICHOLKAR.
... Applicant
Versus
THE EXECUTIVE ENGINEER, WORKS DIVISION VI, GTIDC, BICHOLIM AND ANR., ... Respondents Ms. Rawool Snehal Gurunath, Advocate for the Applicant. Ms. Sapna Mordekar, Additional Government Advocate for the Original Appellants-Respondents.
Coram:- C. V. BHADANG, J.
Date:- 16th July 2019 P.C.
The learned Counsel for the applicant is only pressing the application so far as prayer clause 12(c) is concerned for withdrawal of the amount.
2. The learned Additional Government Advocate for the respondents has no objection for permitting the withdrawal subject to the applicants furnishing security to the satisfaction of the Registrar (Judicial) of this Court.
3. In such circumstances, the application is allowed in terms of
MCA/675/2019 prayer clause (c). The applicant is permitted to withdraw the amount subject to furnishing security to the satisfaction of the Registrar (Judicial) of this Court within three weeks from today. "(c) Grant permission to the applicant to withdraw the deposited amount subject to such conditions this Hon'ble Court may deem fit and proper."
4. Civil Application is disposed off.
C. V. BHADANG, J.
arp/*