Bombay High CourtMCA/129/2014allowed
Edc Limited Rep. By Its Deputy General Manager v. D.G.C. Technologies Pvt. Ltd. And 3 ORS.,
2019-03-25Hon'Ble Shri Justice C. V. Bhadang1 pages
IN THE HIGH COURT OF BOMBAY AT GOA
MISC.CIVIL APPLICATION NO. 129 OF 2014 IN STAMP NUMBER MAIN NO. 2602 OF 2013 EDC LIMITED REP. BY ITS DEPUTY GENERAL MANAGER ... Applicant
Versus
D.G.C. TECHNOLOGIES PVT. LTD. AND 3 ORS., ... Respondents Mr. S. P. Munj, Advocate for the Applicants.
Coram:- C. V. BHADANG, J.
Date:- 25th March 2019 P.C.
This is an application for condonation of delay of 42 days in filing an appeal. The respondents are served, however, have chosen not to appear.
2. For the reasons mentioned in the application, the same is allowed. The delay is condoned. Let the appeal be registered. The office to register the appeal. The appeal to stand over for admission on 01.04.2019.
C. V. BHADANG, J.
arp/*