Union Of India/Govt. Of India, By Its Executive Engineer, Bambolim., v. Shine Enterprises.,
IN THE HIGH COURT OF BOMBAY AT GOA
MISC.CIVIL APPLICATION NO. 733 OF 2017 IN STAMP NUMBER MAIN NO. 2908 OF 2017 UNION OF INDIA/GOVT. OF INDIA, BY ITS EXECUTIVE ENGINEER, BAMBOLIM., ... Applicant
Versus
SHINE ENTERPRISES., ... Respondent Adv. Mahesh Amonkar for the Applicant.
Adv. P. Talaulikar for the Respondents.
Coram:- C. V. BHADANG, J.
Date:- 8th February 2018 P.C.:
On the basis of the judgment of Division Bench of this Court in the case of OIL & NATURAL GAS CORPORATION LTD. VS. DINAMIC CORPORATION 2013 (2) Bom. C. R. 362 it is not disputed that an application for condonation of delay would lie. There is a day's delay in filing the appeal. On hearing the learned counsel for the parties and for the reasons stated therein the same is allowed. Let the appeal be registered. The appeal to stand over for admission on 15/2/2018.
C. V. BHADANG, J.
ap/-