IN THE HIGH COURT OF BOMBAY AT GOA

CIVIL REVISION APPLICATION NO. 6 OF 2020 TIMBLO ENGINEERING PVT. LTD., THR. ITS VICE PRESIDENT-FINANCE AND AUT. SIGN., ANANT FONDU LAWANDE., VS GAMMA IRON INDIA LTD.

... APPLICANT ... RESPONDENT ****** Advocate Peppino Bahl I/b Law Offices of Divya Bahl for the Applicant.

CORAM:

B.P. COLABAWALLA, J.

DATED:

7th JANUARY 2023 P.C.

1.

The above matter has been placed on Board as there was a question of maintainability of the above Civil Revision Application.

2.

The learned Advocate appearing on behalf of the Applicant fairly pointed out that by virtue of the provisions of Section 8 of the Commercial Courts Act, 2015, the present Civil Revision Application filed under Section 115 of the Code of Civil Procedure, 1908, would not be maintainable. She, therefore, sought leave to 7th January 2023

14 CRA 6 OF 2020.ODT withdraw the same with liberty to file appropriate proceedings to challenge the order impugned in the above Civil Revision Application.

3.

In these circumstances, the above Civil Revision Application is dismissed as withdrawn with liberty as prayed. No order as to costs.

4.

This order will be digitally signed by the Private Secretary/Personal Assistant of this Court. All concerned will act order.

B.P. COLABAWALLA, J.

ESHA SAINATH Date: 2023.01.09 10:35:51 +05'30'