IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIRCUIT BENCH AT KOLHAPUR CIVIL APPELLATE JURISDICTION INTERIM APPLICATION NO. 8671 OF 2025 IN FIRST APPEAL (ST) NO. 3389 OF 2025 The Executive Engineer Doodhganga Patbhandare Prakalp ...Applicant

Versus

Janardan Ramchandra Mahadeshwar And Ors.

...Respondents

WITH INTERIM APPLICATION NO. 8672 OF 2025 IN FIRST APPEAL (ST) NO. 3389 OF 2025 The Executive Engineer, Doodhganga Patbhandare Prakalp ...Applicant

Versus

Janardan Ramchandra Mahadeshwar And Ors.

...Respondents

.....

Mr. Shubham Vasekar i/by Adv. Sachin Gite, Advocate for the Applicant.

None for the Respondent.

CORAM :

SHIVKUMAR DIGE, J.

DATE :

15th OCTOBER 2025 P.C.:

INTERIM APPLICATION NO. 8671 OF 2025 1.

Heard learned counsel for the applicant.

1/2

144-IA-8671-2025 (C).doc 2.

Considering the submissions of the learned counsel for the Applicant and the reasons mentioned in the Application, the delay of 380 days for filing the Appeal is condoned. The Application is allowed and disposed of.

3.

The Appeal be registered.

INTERIM APPLICATION NO. 8672 OF 2025 1.

Learned counsel for the Applicant submits that Applicant has deposited entire award amount along with interest thereon. 2.

Considering the submissions of the learned counsel for the Applicant and reasons mentioned in the application, the impugned order is stayed till final disposal of the appeal. Application is disposed of.

FIRST APPEAL (ST) NO. 3389 OF 2025 1.

Issue notice to the respondents, returnable on 27th November 2025.

2.

Interim relief granted earlier shall continue to operate till the next of hearing.

[SHIVKUMAR DIGE, J.] 2/2