← Library
Bombay High CourtCAF/2206/2017

Icici Lombard General Insurance Through Its Authrised Representative Mr.Amol Shirolkar v. Smt.Suvarna Laxman Bhingare And ORS.

2018-09-19Hon'Ble Smt. Justice Dr. Shalini Phansalkar-Joshi1 pages

Dixit

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO.2206 OF 2017 IN FIRST APPEAL (STAMP) NO.4056 OF 2017 ICICI Lombard General Insurance Co. Ltd.

.... Applicant V/s.

Suvarna Laxman Bhingare and Ors.

.... Respondents Ms. Deepali Motagi, I/by M/s. Res Juris, for the Applicant-Insurance Company.

Mr. Vaibhav R. Gaikwad for Respondent Nos.1 to 6. CORAM : DR. SHALINI PHANSALKAR-JOSHI, J.

DATE : 19 TH SEPTEMBER, 2018.

P.C. :

1.

Heard Ms. Motagi, learned counsel for the Applicant-Insurance Company, and Mr. Gaikwad, learned counsel for Respondent Nos.1 to 6. Respondent No.7 has remained absent, though duly served with the notice.

2.

This is an application seeking condonation of delay of 25 days in preferring the First Appeal.

3.

For the reasons stated in the Civil Application, as sufficient cause is made out, the delay is condoned.

4.

Civil Application is allowed, with no order as to costs. [DR. SHALINI PHANSALKAR-JOSHI, J.] 1/1 CAF-2206-17==.doc