← Library
Bombay High CourtIA/4443/2023allowed

Ratnagiri Wind Power Projects Pvt. Ltd. v. Government Of Maharashtra Thr The Secretary And ORS

2023-06-14Hon'Ble Shri Justice Dhiraj Singh Thakur,Hon'Ble Justice Shri Arif S. Doctor2 pages

12 WP.12697.2018 AS.doc

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION WRIT PETITION NO. 12697 OF 2018 WITH INTERIM APPLICATION NO. 4443 OF 2023 IN WRIT PETITION NO. 12697 OF 2018 M/s. Ratnagiri Wind Power Projects Private Limited

...Petitioner

Versus

Government of Maharashtra Through the Secretary Energy Department, Mumbai & Ors.

...Respondents

**** Mr. Bimal Rajasekhar, Advocate for the Petitioner. Mr. A. I. Patel, Addl. GP a/w Mr. B. V. Samant, AGP for the State. Mr. Abhijeet Joshi, Advocate for Respondent No. 3. Mr. Ratnakar Singh, Advocate for Respondent No. 2. **** CORAM : DHIRAJ SINGH THAKUR AND ARIF S. DOCTOR, JJ.

DATE : 14th JUNE, 2023.

P.C.:

.

Interim application No. 4443 of 2023 has been fled for purposes of amending the petition.

2.

We have heard learned Counsel for the parties. R.V. Patil

12 WP.12697.2018 AS.doc 3.

We allow the application in terms of prayer clause (a). Reverifcation is dispensed with. Amended petition be fled within six weeks from today. Copy of amended petition also be served upon learned Counsel for the Respondents. The interim application is disposed of.

4.

List writ petition on 27th July, 2023.

(ARIF S. DOCTOR, J.) (DHIRAJ SINGH THAKUR, J.) R.V. Patil