IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO.1 OF 2020 IN FIRST APPEAL (STAMP) NO.21162 OF 2018 Maharashtra Krishna Valley Development Corpn. ...Applicant V/s.

Sunita A. Kanekar, since deceased through Her L.Rs. - S.A. Kanekar & Ors.

...Respondents

Mr.Siddharth Chapalgaonkar i/b Mr.Nitin P. Deshpande for the Applicant / Appellant.

Mr.Gaurav Potnis for the Respondent Nos.1-A to 1-D and 2. Mr.A.R. Patil, Additional Government Pleader for the State - Respondent Nos.3 and 4.

CORAM : R.D. DHANUKA, J.

DATE : 11TH FEBRUARY, 2020.

P.C. :- 1.

The papers are allowed to be produced at 3.00 p.m. 2.

Not on board. By consent taken on board.

3.

There is delay of 366 days in filing the first appeal. 4.

Heard learned counsel of the parties. Learned counsel for the respondents states that the delay is not explained sufficiently in the civil application.

5.

I have perused the averments made in the civil 1/2

525-caf2755-18.doc application. The delay is sufficiently explained in paragraph 2 of the civil application. The civil application is made absolute in terms of prayer clause (A). There shall be no order as to costs. (R.D. DHANUKA, J.) 2/2